1) Demolition or clean all trees or weeds
2) Riffing dirt and water on land for Developments
3) Import or Export Dirt
4) Compass dirt 95% (Pass soil test)
5) Trenching : Storm drain, Electrical, Water line , Sewer line
6) Engineer will make finished floor Then Minh will trench foundation ( Deep, Rebars, Forming )
7) After pass foundation inspection, then framing, pass framing then do electrical, gas line , water line , insulation, installing sheet rock, tapping, painting, installing cabinet, granite slab counter top, tile for bathroom, hardwood floors, stucco,
8) Call Final Inspection
ALL PROJECT WILL COORDINATE WITH ENGINEERS AND CITY INSPECTION